Hi everyone,
I'm trying to use the scrum component and upon filling my timesheet, I got this error :
"Don't allow actual hours is more than plan hours on Task Id : 10017"

I understand that the number of hours I spent on the task was greater than the one I planned to but, am I not allowed to do that in a scrum driven project ? I'm new to the scrum method so maybe it is a dumb question. Moreover, you can update those "plan hours" directly from the timesheet. It feels a little weird. What do you think ?

Have a nice day,


Florian montalbano

Reply via email to