Hi Divesh,
OFBiz MRP run is essentially single-facility-scoped i.e. it resolves one
facilityId up front (from facilityId or facilityGroupId). It looks like the
recorded MrpEvent.facilityId is essentially informational. As nothing in the
algorithm reads it back, so the gap as such has no functional effect.

However, you may still like to check if there is any case where multiple
events for the same product/date combo could get silently merged across
facilities as it might create a false sense of per-facility separation while
the quantities still collapse together.

Regards,
Swapnil

-----Original Message-----
From: Divesh Dutta <[email protected]>
Sent: 17 July 2026 11:37
To: [email protected]; ofbizuser <[email protected]>
Subject: Proposal: Preserve known facility context on MRP events generated
by the OFBiz MRP engine

Hi all,

I would like to propose an improvement to the OFBiz MRP engine around how it
generates MrpEvent records.

Today, the OFBiz MRP engine can create MrpEvent rows without facilityId even
when the planning signal being processed is already tied to a specific
warehouse or manufacturing facility. In other words, the engine often
already has facility context available while processing demand, supply,
requirements, production runs, or stock policy records, but that context is
not always preserved on the generated MRP event.

This becomes a problem for planners because the event stream loses
warehouse-level traceability even though the source planning data was
facility-aware.

In practice, this can lead to issues such as:


   - Product-plus-facility event timelines being incomplete or harder to
   trust
   - Proposed supply appearing disconnected from the warehouse or plant it
   is intended for
   - Exception or setup views showing events as effectively unassigned
   - Multi-warehouse planning becomes harder to interpret once source
   records are converted into MRP events


The core idea behind this proposal is simple: when the OFBiz MRP engine
already has a reliable facilityId in hand while creating an event, it should
preserve that value on the MrpEvent instead of dropping it.

This is not meant to force facility assignment onto every planning signal.
If the source record is truly organization-level, or if there is no reliable
facility context available, then the event should remain facility-less.

Below is the proposed stamping behavior by event type.


*For sales order demand (SALES_ORDER_SHIP):*

   - Use the facility from the source query result when one is already
   available
   - If no facility is known, leave the event facility empty



*For approved requirements (PROD_REQ_RECP):*

   - Use the facility already present on the requirement



*For purchase order receipt events (PUR_ORDER_RECP):*

   - Use the current planning facility when the MRP run itself is
   facility-scoped



*For production run demand and receipt (MANUF_ORDER_REQ, MANUF_ORDER_RECP):*

   - Use the facility already associated with the production run



*For stock policy marker events (REQUIRED_MRP):*

   - Use the ProductFacility.facilityId from the source record, since the
   minimum stock condition is facility-specific



*For component requirement events (MRP_REQUIREMENT) created during BOM
explosion:*

   - Use the manufacturing facility of the parent proposed manufacturing
   plan



*For proposed supply events:*

   - Use the planning warehouse for proposed purchase supply
   - Use the manufacturing facility for proposed manufacturing supply



*For MRP error events:*

   - When the error occurs while processing a facility-specific planning
   context, preserve that facility on the error event as well


I would also like to propose a conservative improvement when updating
existing MrpEvent rows. If an existing event was previously created without
facilityId, and a later matching update has a valid facility, then the
missing facility could be backfilled only when the existing value is empty.
This would not overwrite any existing facility assignment, but it would
avoid permanently losing context once it becomes available for the same
merged event.

The benefits for planners are fairly direct:


   - Better product-plus-warehouse event views
   - Clearer traceability for proposed replenishment
   - More accurate understanding of which warehouse or plant an event
   belongs to
   - Improved exception analysis in multi-facility planning
   - Better backend event data for API-first or headless planning
   applications


I believe this is a low-risk improvement because it does not change MRP
quantity calculations, planning rules, or event identity. It simply
preserves facility context that the OFBiz MRP engine already knows at the
time the event is generated.

I would appreciate feedback on this proposal, especially on:


   - Whether this principle makes sense for MrpEvent generation in the
   OFBiz MRP engine
   - Whether any of the event categories above should intentionally remain
   facility-less even when facility context is available
   - Whether conservative backfilling of missing facilityId during event
   merge seems acceptable


Thanks,
Divesh Dutta
www.hotwaxsystems.com