Are you certain your YARN cluster has adequate resources/proper
configuration to run both of these jobs simultaneously. A hang in
ACCEPTED state for a submitted MR job typically means its started, but
lacks adequate resources to schedule further tasks/containers.

The launcher job, i.e. the "oozie job name" job, is the parent java
class invoking job which will wait around until the java application
truly finishes. In case of the java app being an MR job itself, this
means "until the job is complete".

On Thu, Aug 8, 2013 at 10:16 AM, Voronov, Dmitry <[email protected]> wrote:
> I have workflow job with a java action node. Run with Hadoop 2.1.0.2.0.4.0-38 
> and Oozie 3.3.2.2.0.4.0 When I submit the job I see 2 lines in Hadoop 
> Resource Manager screen. 1. with original job name 2. with Oozie job name.
>
> The task with Oozie job name is hanging in "RUNNING" state The task with 
> original name is in "Accepted" state. All that I see in logs is:
>
>      >>> Invoking Main class now >>>
> Heart beat
> Heart beat
> Heart beat
> Heart beat
> ...
>
>
> Thank you



-- 
Harsh J