Hi Shinyoung,

Just drop both the applications in parallel and do not connect them. There can 
be multiple independent paths in the workflow and Airavata will execute them in 
parallel. If you connect the edges (inputs/outputs) then it assumes data 
dependency. You can connect the corners on the nodes which will be shown as 
dotted lines that will create control dependencies -- that is even if you do 
not have data dependency, execute one after another. But your case is simple, 
just have them mutually independent.

Suresh

On Apr 5, 2013, at 5:00 AM, 안신영 <[email protected]> wrote:

> Hi guys!
>  
> Let’s assume that a workflow contains several works(services). Some works are 
> independent with each other, some works are dependent some other works.
> Dependency mean that a work should be executed after another dependent work’s 
> completion.
> In this case, How can I configure some independent work to be executed 
> simultaneously?
> I will run this workflow in HPC cluster.
>  
> Regards,
> Shinyoung.