Yes, you should run them on the same schedule and let Continuum resolve the dependencies between them.

- Brett

On 20/10/2008, at 6:03 AM, [EMAIL PROTECTED] wrote:

Hi,
I have a techincal question
is it ok to schedule two projects belonging to the same group and dependencies between them in the same hour? because I see that continuum resolves dependencies between the two projects, if carried out by console,
is this true even when they are scheduled?

for example I have two projects A and B, with A dependent on B,
can you schedule these at the same time?
or should I say a continuum schedule A before B?


thank you very much
Maria


--
Brett Porter
[EMAIL PROTECTED]
http://blogs.exist.com/bporter/

  • Scheduling [EMAIL PROTECTED]
    • Re: Scheduling Brett Porter