Am 24.09.2011 um 13:21 schrieb Stephen Willey <[email protected]>:
We run a render farm submitting lots of array jobs with large numbers of tasks. There seem to be lots of ways of throttling array jobs and sharing across users, but I'm looking for a way to guarantee a minimum allocation rather than a maximum. An example: 10 machines with X slots each 15 users (a,b,c,d,...o) submit array jobs with 1000 tasks, each of which requires X slots.
X is not the same X like above? Or are you using always machines exclusive per array task?
-- Reuti
We'll assume these array jobs are submitted close enough to each other that they all overlap. At the moment, fair share/functional will have some of everyone's tasks run in an interleaved fashion meaning that 'a' might have tasks 1-300 run and then sit there waiting for a long time before 301-600 run and then maybe another wait before the remaining tasks are run. The behaviour we're looking for is: Once an array job starts running, it should not stop running until it's finished. At least one task from that array job should be running at any given time. So in the example above, the 11th array job to start (determined by priority) would not begin until one of the first 10 had finished. Each job would be guaranteed a minimum of at least X slots at any given time (determined by the PE submission option). When not using array jobs, you can just use the FIFO scheduler, but I haven't yet found a way to get to this with array tasks. If anyone's got any ideas it'd be much appreciated, -- Stephen http://lensframephoto.com _______________________________________________ users mailing list [email protected] https://gridengine.org/mailman/listinfo/users
_______________________________________________ users mailing list [email protected] https://gridengine.org/mailman/listinfo/users