Hey everyone, we have been running our sge for a while now but we implemented a new technique and I'm having trouble figuring out how to make the grid help with it.
I have the following task / dependency structure. task1 task2_seed_0 = dependent on output of task1 task2_seed_1 = dependent on output of task1 task2_seed_2 = dependent on output of task1 task2_seed_3 = dependent on output of task1 joiner = dependent on output of seed tasks. all of these are Parallel environments with a range from 1-100 and a batch of 1 now what I would like to happen is that the Grid finishes doing the first batch of task 1. then all 4 of the task2 will get there first batch started. what's currently happening is that sge tries to schedule and finish all of task2_seed_0 before moving on to the task2_seed_1. anyone have a idea on how to get this behaviour? Lars _______________________________________________ users mailing list [email protected] https://gridengine.org/mailman/listinfo/users