We build official releases "manually". But Dan's suggestion seems reasonable.
Wayne On 7/21/06, dan tran <[EMAIL PROTECTED]> wrote:
you can add a build defintion to you current project that do this. mvn scm:bootstrap -Dgoals="-B,release:prepare,release:perform" schedule it to somewhere in far future and run it ( one click) later never try it thou ;-) -D On 7/21/06, [EMAIL PROTECTED] <[EMAIL PROTECTED]> wrote: > > I was wondering if anyone has developed any best practices for performing > a release with maven when using continuum? To cut things down to the basics, > seems you pretty much have to: > > 1. Stop continuum > 2. Perform the release (including deployment of jars to repository) > 3. Restart continuum > > Is this pretty much what everyone else is doing, or have other people > found better ways of managing releases in a continuous integration > environment. > > Thanks, > Baron >