On Friday 26 August 2005 03:03 pm, Adam Pearson wrote:
I have 6 houses at this time. I do Shelving, Mirrors, Door Hardware, Bath 
Hardware, and Shower doors/Enclosures.. I just need to keep track of when the 
sheetrock is in, when they are painted and when the counter tops are in. and 
if there is a closing date. I would like to show a projected date on these 
few items. 
> Richard Barmann wrote:
> >Is there a Template or can you advise me on how to keep track of several
> >houses under construction, They are all at different phases of completion.
>
> Richard
>
> How many houses have you got to deal with?
>
> How do you assess how complete the houses are?  Do you/are you able to
> express it as a percentage?  If so, then you could just list all the
> houses in a column on Calc, then enter the percentage complete.
>
> If assessing % complete is not convenient, you could establish a
> duration for each phase of each house's construction - eg:
>
> prepare site, underground services, lay foundations: 3 weeks;
> floor: 1 week;
> wall frames: 3 weeks
> roof and roof cladding: order and deliver trusses, 8 weeks from
> commencement;
> roof cladding: 2 weeks
> wall linings: 2 weeks
> etc
> etc
>
> Then use a spreadsheet to list the activities in the first column, give
> each activity two rows, fill in the planned weeks like a bar/gantt chart
> with a fill colour and use the second of each activity's rows to mark
> actual progress.  For example, use dark blue/light blue to show
> planned/actual progress.
>
> You could set up each house on a separate sheet.
>
> If that's not clear, I can construct and send you a sample directly if
> you want.
>
> Regards
>
> Adam
>
> ---------------------------------------------------------------------