Regarding my previous note about refurbishing of the UK's National Grid system. 
 I forgot to mention that the refurbishing of the steel towers has been a huge 
problem, in that the towers, dating from the early 1960s, are all constructed 
from imperial steel angle shapes.  These shapes have long disappeared, and all 
steel angles are hard metric sizes (150 x 150 x 6, etc). (Rolled steel 
wideflange beams etc are still in old imperial sizes, even if they are given a 
metric designation.)

In replacing a newly discovered rusted out angle on these towers, the new 
metric angle often would not fit, resulting in all kinds of lash-ups and other 
quick fixes.  And they had to be quick - a section of the grid (say one side of 
a 40 km stretch of line) had a very specific outage window, timed to the 
minute, with huge penalties if the contractor ran over time (sometimes the 
crews were working round the clock to stay within the window).  Thus there 
wasn't time to re-engineer the steel angle framing (and new cables could not be 
strung until the tower WAS fixed) - it was truly a fix-as-you-go solution.  One 
only hopes that the quick fix has an equal or greater degree of structural 
integrity as the original design....

Of course, if National Grid had conducted a full PSE (pre-sanctioned 
engineering) survey of every tower on any particular line, instead of the cheap 
solution of just taking a random sample of towers, these problems could have 
been avoided.  A true case of "A gram of prevention is worth a kilo of cure".

John F-L

Reply via email to