Oops, thanks to Stefaan and Simon. I suppose everyone gets to make one
stupid mistake per month. Since we needed to upgrade all our hardware
this is actually an all new installation and I missed that setting. I
wonder what else I missed. Anyway, thanks again.
David Spearman
County of Hnerico, Va.
-----Original Message-----
From: Stefaan Margot [mailto:[EMAIL PROTECTED]
Sent: Wednesday, April 23, 2008 7:17 AM
To: Spearman, David
Subject: Re: [Veritas-bu] NBU 6.5.1 multistreaming problem
David,
have you checked the "max number of jobs per client" setting?
regards,
stefaan.
________________________________
From: Spearman, David [mailto:[EMAIL PROTECTED]
To: [email protected]
Sent: Wed, 23 Apr 2008 12:43:08 +0200
Subject: [Veritas-bu] NBU 6.5.1 multistreaming problem
We have recently moved from 6.0 mp4 to 6.5.1 (windows).
The first major
problem we have run in to is multistreaming. Even though
our policy is
set up identically as on 6.0 when the job kicks off it
sets all the
streams in the queue but the streams only run one at a
time. The other
streams are awaiting resources. Since the drives are set
to multiplex at
a higher level than the number of stream this should not
be happening as
indeed it worked just fine with 6.0. Has anyone else
experienced this
problem?
David Spearman
County of Henrico, Va.
_______________________________________________
Veritas-bu maillist - [email protected]
http://mailman.eng.auburn.edu/mailman/listinfo/veritas-bu
_______________________________________________
Veritas-bu maillist - [email protected]
http://mailman.eng.auburn.edu/mailman/listinfo/veritas-bu