The Multipurpose Applied Physics Lattice Experiment reactor was meant to
produce medical isotopes.
For safety reasons MAPLE was designed to have a negative power coefficient
but it has been plagued by an unexpected positive power coefficient for
years. (The project was terminated in May).

Is it possible that the designers of MAPLE  unwittingly created the
conditions for cold fusion?

Please consider the article below.
I will see if I can find a diagram of the reactor.
Harry


http://www.cmaj.ca/cgi/content/full/178/7/813

Over budget, overdue and, perhaps, overdesigned
Ben Magnus 

Ottawa, Ont. 

They have become an enduring Canadian mystery. They were originally
scheduled to become operational in November 2000, providing Canada with a
long-term secure supply of medical isotopes.

Yet, years later, the once highly lauded Multipurpose Applied Physics
Lattice Experiment (MAPLE) reactors are still in limbo because of technical
difficulties, and Canada's 50-year-old National Research Universal reactor
is being pressed into service well beyond its original projected lifetime.

The MAPLEs were to have been the first reactors in the world dedicated
exclusively to the production of medical isotopes, which are used for
diagnostics and the destruction of tumours or cancerous cells through gamma
rays or manufactured drugs

The reactors were said to have the capacity to supply double the worldwide
demand, yet with their future so uncertain, it's unclear when, or if,
they'll ever serve as a secure source of supply in Canada, let alone the
world. 

Isotope supplier MDS Nordion when the had originally hired the crown
corporation Atomic Energy of Canada Ltd. (AECL) to design and construct 2
MAPLE reactors and a processing facility in Chalk River, Ontario, in 1996.
Aided by an interest-free loan from the federal government, the firm agreed
to pony up $140 million for construction of the reactors. Radioisotope
production had historically been vested with AECL but the government moved
to private it in the late 1980s and eventually found a willing buyer, in
1991, in the form of MDS Health Group Inc., for $165 million.

In a 2005 renegotiation of the contract between MDS Nordion and AECL,
ownership of the Dedicated Isotope Facility was transferred to AECL in
exchange for $68 million in cash and promissory notes, as well as a 40-year
commitment to supply Nordion with isotopes, the value of which was pegged at
$344 million. MDS Nordion promptly wrote off a $345 million loss.

Under the agreement, AECL absorbed all remaining MAPLE development,
construction and operational costs. In AECL's 2006/2007 Summary Corporate
Plan, the projected cost of completing the project was estimated at $130
million. 

More current numbers have not been publicly disclosed, although a Sept. 5,
2007, report from the Office of the Auditor General indicated AECL forecasts
the cost of overhauling its Chalk River infrastructure, including MAPLEs, at
$600 million over the next 5 years and $850 million over 10 years. The
federal government's Feb. 26th budget shovelled $300 million towards that
effort. 

According to some nuclear experts, the additional outlays and extended
timeline are no guarantee that the facilities will be ready by the current
target deadline of Oct. 2008.

Among the skeptical are Fred Boyd, who spent more than 50 years in the
nuclear industry working with AECL, its regulator the Atomic Energy Control
Board (now the Canadian Nuclear Safety Commission), the Department of Energy
Mines and Resources (now Natural Resources Canada), and who remains a
regular contributor to the Canadian Nuclear Society Bulletin.

Boyd fears that fundamental design flaws and testing requirements will
continue to delay the project. "I think the most optimistic would be at
least a year and I guess I am sufficiently pessimistic at the moment that it
would be longer than that."

The issue that has continuously perplexed designers of the MAPLE reactors
has been their positive power coefficient reactivity (Box 1).


View larger version (89K):
[in this window]
[in a new window]

      Box 1.
 

For safety reasons, the reactors were designed to have a negative power
coefficient reactivity value. It was expected to be ­0.12 mk/MW. In June
2003, it was measured at +0.28 mk/MW.

Since then, AECL has tested and re-tested its predictions and results.
Experts from around the world have been recruited to help solve the riddle.
Argentina's Investigacion Aplicada was hired, along with a bevy of American
contractors. To date, their reviews have confirmed that all AECL
measurements and data analyses were done correctly.

Yet, no amount of analysis, fiddling or technological repair has resolved
the deviation from original design. Tests in 2007 achieved the exact same
+0.28 mk/MW measurement.

But AECL Director of Corporate Communications Dale Coffin insists that "we
have made some progress."

Coffin says the next tests will be completed this spring, again under the
watchful eye of the Canadian Nuclear Safety Commission, and will determine
the direction for future AECL action as the MAPLES start-up date looms.

It begs the question: Is it even possible that the problems will be resolved
by the fall? 

The answer to that, it seems, is to alter the nature of the inquiry.

Boyd and other experts argue that because the reactor is only slightly
positive and because there are potential shutdown mechanisms and
precautionary measures, it should be possible to to simply steam forward.
"The actual risk is quite small," Boyd says.

You can never eliminate all risk, he muses, adding that while not desirable,
it makes sense to move forward with licensing and operation activities
without fully understanding the problem.

The process has been overly cautious, Boyd argues. "The desire has been and
this has been a tendency throughout the world the last 10 or 20 years,
prompted by the one bad accident at Chernobyl, that people in the nuclear
business have been leaning over backwards to try and make things more
inherently safe." 

AECL has flashed indications that it is moving towards a similar conclusion.
Coffin, for example, stresses that the actual results of the power
coefficient reactivity are "so close to being negative."

The crown-owned company has also told safety regulators that it may want to
move forward with licensing, even if the problem isn't resolved. In a public
hearing in September 2007, AECL submitted a plan that deemed "low or
negative" power coefficient reactivity as acceptable, even though that was
contrary to the original design.

Safety commission staff initially maintained that AECL should be working
towards a negative value, in order to support the original safety case. But
even the regulator seems to be warming to the notion of licensing positive
value reactors. 

Spokesman Aurèle Gervais confirmed in an email interview that AECL can
submit a safety case with the issue unresolved. But it hasn't yet made such
a submission and hasn't indicated a timeframe in which it might do so.

Commission "staff does not prescribe the 'sign or magnitude' of the [power
coefficient reactivity], but makes recommendations to the Commission on the
basis of acceptability of risk," wrote Gervais. "Staff recommended the
original MAPLE's operating licence based, among other design/physics
characteristics, on the inherent safety provided by a negative [power
coefficient reactivity]."

Yet, even if the crown-owned company and the regulator all agree to move
forward in spite of the positive power coefficient reactivity, problems
remain. 

According to Boyd, designers still haven't resolved how to process the
isotopes that are produced by the reactors.

There are problems surrounding the extraction of the molybdenum isotope
while separating it from the uranium, Boyd says.

"There have been difficulties at the processing facility extracting the
molybdenum isotope, which is the most valuable one, out of the samples. I
have been told there are still some significant problems with the process so
my understanding is that is likely to be the greater impediment for early
startup. So in other words, it will take longer to solve that one than to
solve the MAPLE problems. I don't have any details on that. That is strictly
second and third hand, but from people that I trust and who know something
about what's going on."



Reply via email to