Hi,
jugding from this video at 0:02 they added one steam outlet tube:
<http://youtu.be/uFiJb2UhzqY>
The dimensions of the container are 5.0m x 2.6m x 2.6m
This is mentioned in the final report:
<http://www.nyteknik.se/incoming/article3303693.ece/BINARY/Report+Ecat+Oct28+%28pdf%29>
I downloaded this image of the steam outlet:
<http://www.nyteknik.se/incoming/article3264397.ece/BINARY/original/DSC_0015_400px.jpg>
and scaled it up until the container was 26 cm wide.
Then I measured the diameter of the blue tube, it was 9 mm. So the outer
diameter is 9 cm.
So the real tube inner diameter must be at least 8 cm.
So the crossectional area is 16*3.14 cm^2 = 50.24 cm^2
The old calculations must be corrected, these where based on 33 cm^2,
so far I remember.
Because we have now 2 tubes the total crossectional area must be a
little bit more than 100 cm^2.
Also we have now not 1 MW, but we have 479 kW.
*So the old steam speed calculation is about factor 6 or 7 too high and
must be corrected!*
I did not calculate precise values. Possibly other people have already
done this, but I think, this must be considered.
Best,
Peter