Am 13.11.2011 12:10, schrieb Albert:
A couple of comments:

-There were only two flowmeters on the water from the pumps. The two pumps 
without were not running. (There is a number of valves on the pipes from the 
pumps to the Ecats, but it is hard to know exactly the position on all of them 
from the videos.)
So far I have read there where no flowmeters.
The flow was measured by a scaled reservoir, not continuously, but at any arbitrary time when the customer wanted it. I think the outflow point where it was measured is visible left from the water pumps in the video.
It would be fine to make this obvious in the schematic.
-There was a valve on the connection to the 5l container for non-vaporized 
water, and it was closed.

-I would move the condensers to the bottom of the figure, at the same height as 
the reservoir, as it would make the problem of how the water got back up into 
the latter more visible.
I think this would confuse and clutter the good drawing. This is usually not done in such schematics. In high pressure systems when the level above ground is irrelevant it is not documented.
If it is relevant it can be written into the schematic where needed.
-I got the impression that the reservoir 2 was connected to number 1 by a pipe 
all the time.

-You could add the pressure meters on the outlet of the pumps, and we also know 
the pressure: 3.8 bar.

/A.