[Winona Online Democracy] Yesterday Mike Kirschmann asked for some specific costs of the Lincoln Relocation Plan and how they compared to the original estimates presented to the public.
For the Goodview site the projected renovation cost for remodeling, storage addition and site work was estimated at $267,640. The contractor was awarded the bid at $387,500. The estimate for A&E fees (architect and engineering) was blank, The actual cost was $26,400. There was no mention of the need for a sprinkler system. The contract for the sprinkler system was over $145,000. In addition, the projected costs included $54,459 for furnishings and $23,000 for voice and data. Total projected cost for the Goodview project-including furnishings and voice and data-was $345,099. Actual contracts awarded thus far is $558,900. This figure does not iinclude furnishings or voice/data estimated to be $77,459. Add those estimated costs to the known costs and this project will be $636,359. That would be 84% over the original cost estimates. The scenario for the administration and library/media center renovation at the WSHS appears to be at least double the cost of the original estimates. Gary Shurson 1260 Briarwood Court Minnesota City, MN _______________________________________________ This message was posted to Winona Online Democracy All messages must be signed by the senders actual name. No commercial solicitations are allowed on this list. To manage your subscription or view the message archives, please visit http://mapnp.mnforum.org/mailman/listinfo/winona Any problems or suggestions can be directed to mailto:[EMAIL PROTECTED] If you want help on how to contact elected officials, go to the Contact page at http://www.winonaonlinedemocracy.org