Arun Suresh created YARN-7839:
---------------------------------

             Summary: Check node capacity before placing in the Algorithm
                 Key: YARN-7839
                 URL: https://issues.apache.org/jira/browse/YARN-7839
             Project: Hadoop YARN
          Issue Type: Sub-task
            Reporter: Arun Suresh


Currently, the Algorithm assigns a node to a requests purely based on if the 
constraints are met. It is later in the scheduling phase that the Queue 
capacity and Node capacity are checked. If the request cannot be placed because 
of unavailable Queue/Node capacity, the request is retried by the Algorithm.

For clusters that are running at high utilization, we can reduce the retries if 
we perform the Node capacity check in the Algorithm as well. The Queue capacity 
check can still be handled by the scheduler (since queues are tied to the 
scheduler)



--