Hudson commented on YARN-2008:
------------------------------

FAILURE: Integrated in Hadoop-Hdfs-trunk #1831 (See 
[https://builds.apache.org/job/Hadoop-Hdfs-trunk/1831/])
YARN-2008. Fixed CapacityScheduler to calculate headroom based on max available 
capacity instead of configured max capacity. Contributed by Craig Welch 
(jianhe: 
http://svn.apache.org/viewcvs.cgi/?root=Apache-SVN&view=rev&rev=1616580)
* /hadoop/common/trunk/hadoop-yarn-project/CHANGES.txt
* 
/hadoop/common/trunk/hadoop-yarn-project/hadoop-yarn/hadoop-yarn-common/src/main/java/org/apache/hadoop/yarn/util/resource/DefaultResourceCalculator.java
* 
/hadoop/common/trunk/hadoop-yarn-project/hadoop-yarn/hadoop-yarn-common/src/main/java/org/apache/hadoop/yarn/util/resource/DominantResourceCalculator.java
* 
/hadoop/common/trunk/hadoop-yarn-project/hadoop-yarn/hadoop-yarn-common/src/main/java/org/apache/hadoop/yarn/util/resource/ResourceCalculator.java
* 
/hadoop/common/trunk/hadoop-yarn-project/hadoop-yarn/hadoop-yarn-common/src/main/java/org/apache/hadoop/yarn/util/resource/Resources.java
* 
/hadoop/common/trunk/hadoop-yarn-project/hadoop-yarn/hadoop-yarn-server/hadoop-yarn-server-resourcemanager/src/main/java/org/apache/hadoop/yarn/server/resourcemanager/scheduler/capacity/CSQueueUtils.java
* 
/hadoop/common/trunk/hadoop-yarn-project/hadoop-yarn/hadoop-yarn-server/hadoop-yarn-server-resourcemanager/src/main/java/org/apache/hadoop/yarn/server/resourcemanager/scheduler/capacity/LeafQueue.java
* 
/hadoop/common/trunk/hadoop-yarn-project/hadoop-yarn/hadoop-yarn-server/hadoop-yarn-server-resourcemanager/src/test/java/org/apache/hadoop/yarn/server/resourcemanager/scheduler/capacity/TestCSQueueUtils.java


> CapacityScheduler may report incorrect queueMaxCap if there is hierarchy 
> queue structure 
> -----------------------------------------------------------------------------------------
>
>                 Key: YARN-2008
>                 URL: https://issues.apache.org/jira/browse/YARN-2008
>             Project: Hadoop YARN
>          Issue Type: Sub-task
>    Affects Versions: 2.3.0
>            Reporter: Chen He
>            Assignee: Craig Welch
>             Fix For: 2.6.0
>
>         Attachments: YARN-2008.1.patch, YARN-2008.2.patch, YARN-2008.3.patch, 
> YARN-2008.4.patch, YARN-2008.5.patch, YARN-2008.6.patch, YARN-2008.7.patch, 
> YARN-2008.8.patch, YARN-2008.9.patch
>
>
> If there are two queues, both allowed to use 100% of the actual resources in 
> the cluster. Q1 and Q2 currently use 50% of actual cluster's resources and 
> there is not actual space available. If we use current method to get 
> headroom, CapacityScheduler thinks there are still available resources for 
> users in Q1 but they have been used by Q2. 
> If the CapacityScheduelr has a hierarchy queue structure, it may report 
> incorrect queueMaxCap. Here is a example
>                              ||                    ||rootQueue||     ||
> |  |                               /                               |          
>           \                     |
> |      L1ParentQueue1                      |          |            
> L1ParentQueue2    |
> |  (allowed to use up 80% of its parent)    |  |         (allowed to use 20% 
> in minimum of its parent)|
> |                    /   |     \ |                            |  
> |  L2LeafQueue1 |    L2LeafQueue2 |  |     
> |(50% of its parent) |  (50% of its parent in minimum) |   |
> When we calculate headroom of a user in L2LeafQueue2, current method will 
> think L2LeafQueue2 can use 40% (80%*50%) of actual rootQueue resources. 
> However, without checking L1ParentQueue1, we are not sure. It is possible 
> that L1ParentQueue2 have used 40% of rootQueue resources right now. Actually, 
> L2LeafQueue2 can only use 30% (60%*50%). 



--