Current Dev Position: 1.9 Milestone 3 (M3)

Next Deadline: M3 cut off of August 24th at noon GMT (On hold until most likely 
next week)


SWAT team rotation: Beth -> Saul

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

*         M3/Feature freeze is still being worked on and continues to be 
delayed. Many things have merged but there are issues being encountered in some 
areas.

*         Test builds are continuing as fast as the infrastructure allows us to 
validate changes and get them merged.

*         The qemuarm segfault has been resolved.

*         Issues have been encountered in the sdk testing, particularly aarch64 
and those are being addressed. It has highlighted issues with the QA 
infrastructure as well.

*         There were significant issues found  with SIGKILL handling this week 
and those have also been resolved.

*         The mips lsb-sdk sanity test failures look like they're due to mips 
being incredibly slow at running some of the tests and it appears those tests 
have never been run up until some recent configuration changes.

*         There does appear to be a significant cpu usage issue when running 
some of the automated QA tests which also doesn't help our overloaded 
infrastructure.

*         Reminder: The current version that is in development will launch as 
YP 2.0 in October, 2015. We have renamed YP 1.9 M4 to YP 2.0.  This will be the 
stabilization milestone for YP 2.0 release.

*         Since we have passed YP 1.9 M3; we are at YP 1.9 / 2.0 feature 
freeze.   All enhancements now will be pushed YP 2.1.

*         The release name for YP 2.0 is 'jethro'.


Key YP 1.9/2.0 Dates:

YP 1.9 M3 Release Target: Before Sept. 11 2015  (Will be late)

YP 2.0 Final - 2.0 Cut off: Sept. 28, 2015 noon GMT

YP 2.0 final Release Target: Before Oct. 30, 2015


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v1.9_Status

https://wiki.yoctoproject.org/wiki/Yocto_1.9_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_1.9_Features


Tracking Metrics:

            WDD 2154 (last week 2054 )

(https://wiki.yoctoproject.org/charts/combo.html)


[If anyone has suggestions for other information you'd like to see on this 
weekly status update, let us know!]

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*   Work Telephone:          (503) 712-0534
*    Cell:                                (208) 244-4460
* Email:                             [email protected]

-- 
_______________________________________________
yocto mailing list
[email protected]
https://lists.yoctoproject.org/listinfo/yocto

Reply via email to