Attendees: Stephen, Roman, Saul, Belen, Joshua, Maxim, Richard, Sona,


Agenda:



* Opens collection - 5 min (Stephen)

* Yocto Project status - 5 min (Stephen/team)

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.1_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.1_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.1_Features

YP 2.0.1 is about to be publicly release later this week.

YP 2.1 M2 was released last week.

YP 2.1 M3 is being built.  As soon as it is stable we will put it into QA for 
evaluation.

* Opens - 10 min

Belen - Discussed HOB removal.  HOB has been removed from the YP 2.1 code base. 
 Toaster has replaced the functionality of HOB.

OEDAM is in San Diego after ELC.  Watch for an e-mail to the lists discussing 
this.

* Team Sharing - 10 min




Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*   Work Telephone:          (503) 712-0534
*    Cell:                                (208) 244-4460
* Email:                             stephen.k.jol...@intel.com

-- 
_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto

Reply via email to