Tim

This is probably why you had an outage today. Your provider should have 
notified you of this in advance.

There were troubles during this maintenance today that caused generator power 
to be lost to some parts of the building. Luckily for us our equipment is not 
located in the sections that were affected.

We had our own staff on site all day "just in case". Not sure about your 
provider, but I believe they have representatives on this list and they may 
address this issue. ( I will leave them nameless as well )

Bill

-----Original Message-----
Sent: April 18, 2009 5:59 AM
Subject: FW: **Maintenance Notification Update**


*Scheduled Maintenance Update*

Date: April 18, 2009
Time: 06:00hrs EST

ยท         Update: Maintenance window is now OPEN to perform the scheduled 
maintenance listed below

During the hours: 06:00hrs until 20:00hrs Local time at the site, on Saturday, 
April 18 we will be performing the following activities:

* 151 Front Street will be performing their annual building shut down. *

During the above maintenance window, all commercial power to the building will 
be disconnected for maintenance and upgrades.  All suites will transfer to 
Generator Power for the duration of the window.

**NO SERVICE INTERUPTION IS EXPECTED**

Unless otherwise indicated, the scope of work to be performed by the building 
will include:

600 volt cell for switch board 175
An additional 13.8kv cell, located in the main hydro vault
Thermal Scan on all electrical room services
Ultra sound of HV Cells
Complete inspection of all Hydro Vault electrical services
Repair of any deficiencies uncovered during the required inspection

***Please note, there will only be limited access to the building/equipment 
during the above operational window.  Staff will be on site to handle any 
technical/emergency needs***

If you have any questions or comments about the above maintenance, please 
contact us.

Thank you for your cooperation.