None that I can think of. I would thing the restart procedure would be more 
important. Get the external connection up first, then work inward.  In AD, 
start with FISMO, in the root domain, then down/outward to the branches.

Sent from my iPad

On Jul 18, 2013, at 11:37 AM, "Kennedy, Jim" <kennedy...@elyriaschools.org> 
wrote:

> We are shutting our data center down for 7 days to repair the 
> HAVAC/Electrical systems.  Long story but it needs to be done this way. Since 
> we are a school district and it is summer we are just going to pull the plug 
> on the network and let that summer staff fend for themselves. I have a 
> secondary MX up with a hold and forward.
>  
> There are 4 offsite DC’s that could be left running, but they will not be 
> able to talk to each other, their connectivity is via the data center.  I am 
> thinking shut them down too.
>  
> Any issues or concerns that come to mind for a week long downtime for AD?