------------------------ Yahoo! Groups Sponsor --------------------~--> 
Yahoo! Domains - Claim yours for only $14.70
http://us.click.yahoo.com/Z1wmxD/DREIAA/yQLSAA/1TwplB/TM
--------------------------------------------------------------------~-> 

Dawn [Pakistan]
25 July 2004

Another nuclear white elephant
By Zia Mian and A.H. Nayyar

Bearing in mind the fact that the Chashma-I nuclear power plant has 
proved nothing to write home about, there seems to be little 
justification for the Chashma-II project. Are all things nuclear 
above the law?

Pakistan has signed up to buy its second Chinese-made nuclear power 
plant. This new plant will be identical to the earlier reactor at 
Chashma, designed and built by the Chinese, on the banks of the Indus 
River, about 30 miles from Mianwali. The project has been given the 
go-ahead despite the fact that the experience with the first reactor 
has not been encouraging. Economic factors related to the project are 
dubious and many questions that were raised about the safety of the 
Chinese design and the location of the first reactor at Chashma 
remain unanswered.
The deal for the Chashma-II nuclear power plant was signed in May 
this year. It is said that the reactor will be built in less than 
seven years, with some reports suggesting it might start operating by 
2010. But building a nuclear power plant is no simple matter. There 
were similar claims about the Chashma-1 plant. When the Chashma-1 
contract was signed at the end of 1991, it was thought that the 
reactor would start operating in six years. But it took almost nine 
years before it was finally handed over by the Chinese to the 
Pakistan Atomic Energy Commission (PAEC) in late 2000, and it was 
only formally inaugurated in early 2001. It is quite likely that the 
schedule for Chashma-II will slip too, and it may be closer to 2015 
before the reactor starts producing electricity.
Economics factors related to nuclear electricity are quite mysterious 
in Pakistan, since the PAEC cloaks itself in secrecy and seems 
reluctant to give away any kind of detailed accounts. But it was 
reported that the Chashma-1 reactor cost somewhere between $600 
million and over $1 billion. Some informed sources suggest the actual 
cost was about $1.3 billion, that is, approximately double the cost 
that was originally claimed. This is a staggering figure considering 
that the plant was designed to produce only 300MW, meaning over $4 
per MW of electrical power capacity. For comparison, this is more 
than twice the cost for every megawatt of electricity generating 
capacity from the Ghazi Barotha hydroelectric project inaugurated by 
President Musharraf in August 2003. It has been reported that 
Pakistan has budgeted Rs54.392 billion for the Chashma-II reactor. As 
with Chashma-1, the actual final cost is likely to be higher.
The operating costs of nuclear reactors (per unit energy produced) 
are invariably higher than those of a thermal power plant. This is 
true in Pakistan's case. Thus the electricity produced by nuclear 
power plants is bound to be costlier.
While China designed and built the Chashma-1 project, which the PAEC 
now operates, it is Wapda that has to buy electricity (to distribute 
it for domestic use etc). In 2003, Wapda complained publicly that it 
was being forced to pay almost twice what it should for electricity 
generated through Chashma-1. The electricity that Wapda produces and 
buys from independent power producers is much cheaper than what is 
being charged by the PAEC for Chashma-1. The dispute over price 
between them was eventually settled after the government intervened 
and forced Wapda to pay some extra amount. Wapda officials have 
argued that this is causing them an annual loss of Rs3 billion. One 
senior official is of the view that the Chashma-1 plant is "going to 
eat our revenues for decades". There is no reason to expect that 
electricity generated by Chashma-II will be any cheaper. But whatever 
the cost may be, Wapda and electricity consumers will have to pay.
Wapda officials have also protested that the Chashma-1 project is not 
a reliable one, compared to its own power plants or the ones run by 
commercial independent power producers. They say the plant has been 
frequently shut down without any prior warnings and requires long 
maintenance periods. For instance, according to the PAEC's own 
reports, in 2002-2003, the project remained out of operation for 
nearly 175 days. In one incident, it took the authorities 33 days to 
repair a breakdown.
Part of the problem is that Chashma-1 is one of those plants that are 
called 'turn-key' projects. The design is Chinese and all the major 
components were made in China. All Pakistan did was pay for it and 
turn the key to start it. The Chashma-II plant will be the same, 
because the PAEC is not involved in the basic design and engineering 
work. Therefore, if something goes wrong they will not be able to fix 
it. In such a situation, Chinese engineers have to be called upon to 
fix the plant. They charge extra for this, of course. There is little 
incentive for them to let Pakistani engineers take part in the repair 
work. So the PAEC remains dependent on Chinese expertise.
This is a more serious problem than it may appear. While the PAEC is 
clearly operating a reactor of which it has very little experience, 
it is also not clear whether China has the required competence.
Chashma-1 and Chashma-II plants are based on a Chinese prototype 
reactor that was built in 1990. Owing to serious design problems, 
China decided not to build any more for itself. Instead, it first 
sold one copy, and now a second, to Pakistan. The original Chinese 
reactor (at Qinshan) suffered an accident in 1998. The reactor had to 
be shut down for a year. China could not fix the problem, and had to 
contact a US company to do the repair work. This included redesigning 
one part of the reactor. Tens of millions of dollars were paid to the 
American company. If China cannot deal with problems at its own 
indigenously designed reactor, it is by no means clear that it will 
be able to fix all the problems at Chashma-1 or Chashma-II. Perhaps 
the PAEC expects the Americans to come and help.
Other problems include the location of the reactors. It is close to 
the banks of the Indus River in an area where there may be 
earthquakes and where the properties of the soil may make the effects 
of an earthquake more severe than otherwise. An accident, God forbid, 
would have very serious consequences. In case of a large release of 
radioactivity, as happened at the Chernobyl nuclear power plant in 
1986, Pakistan could face catastrophic problems. Estimates suggest 
that in the long-term there could be over 12,000 cancer-related 
deaths, and perhaps three times as many cases of cancer. There would 
also be radioactive contamination of the land, the Indus River, and 
possibly the groundwater. The effects, as at Chernobyl, could last 
for decades.
These are grave risks to run. They seem foolish given that both 
projects are small power plants, together making up just over three 
per cent of the already installed electricity generating capacity in 
the country. Reducing the enormous power theft in the existing 
electricity distribution system (about 40 per cent) could easily save 
more electricity than would be produced by both these nuclear plants. 
Similarly, investing the same amount of money in electricity 
conservation, for example by making motors, fans, fridges and lights 
more efficient, would go a long way to removing any need for these 
plants altogether.
Poor economics, uncertain safety and potential environmental dangers 
that have surrounded the Chashma-1 plant, all suggest that there 
needs to be a serious public debate before the Chashma-II project is 
allowed to become a reality. The same demand was made about 
Chashma-1. In 2000, a coalition of Pakistani environment groups and 
other NGOs wrote to President Musharraf asking him to stop work on 
Chashma-1 until there had been a detailed public environmental impact 
assessment of the plant. They argued that people are entitled to know 
and decide the dangers that will be run in their name. This kind of 
public assessment is required by the law, under the 1997 Pakistan 
Environmental Protection Act. But since the Chashma-1 plant was 
almost operational, the PAEC refused to admit that any public 
assessment was needed or possible, and the government just went 
along. The environmentalists were ignored.
It is not too late to do the right thing about the Chashma-II Nuclear 
Power Plant. This project is still on the drawing board and there is 
still plenty of time for a public environmental impact assessment. It 
remains to be seen if all things nuclear prove to be beyond the law, 
beyond public debate and beyond reason.


_________________________________

SOUTH ASIANS AGAINST NUKES (SAAN):
An informal information platform for
activists and scholars concerned about
Nuclearisation in South Asia

South Asians Against Nukes Mailing List:
archives are available @ two locations
May 1998 - March 2002:
<groups.yahoo.com/group/sap/messages/1>
Feb. 2001 - to date:
<groups.yahoo.com/group/SAAN_/messages/1>

To subscribe send a blank message to:
<[EMAIL PROTECTED]>

South Asians Against Nukes Website:
www.s-asians-against-nukes.org



-- 

SOUTH ASIANS AGAINST NUKES (SAAN):
An informal information platform for activists &amp;amp; scholars concerned about the 
dangers of Nuclearisation in South Asia

SAAN Mailing List:
To subscribe send a blank message to: 
[EMAIL PROTECTED]

SAAN Website:
http://perso.wanadoo.fr/sacw/saan
[OLD URL: http://www.mnet.fr/aiindex/NoNukes.html ]

SAAN Mailing List Archive :
http://groups.yahoo.com/group/SAAN_/ 
________________________________
DISCLAIMER: Opinions expressed in materials carried in the posts do not
necessarily reflect the views of SAAN compilers.
aterials carried in the posts do not
necessarily reflect the views of SAAN compilers.
 

Yahoo! Groups Links

<*> To visit your group on the web, go to:
    http://groups.yahoo.com/group/SAAN_/

<*> To unsubscribe from this group, send an email to:
    [EMAIL PROTECTED]

<*> Your use of Yahoo! Groups is subject to:
    http://docs.yahoo.com/info/terms/
 


Reply via email to