Guido and I did a DR webinar a few months back, and an associated
whitepaper... You can get the whitepaper at
http://www.netpro.com/welcome/disasterrecovery/index.cfm. The last I
looked, you had to register for it (email address, etc.)

We recorded the webinar as well. You can get to it at
http://www.netpro.com/forum/files/AD_Disaster_Recovery.wmv. Same
registration requirements.

We are also hosting an all-day DR pre-conference workshop for DEC this
year. See www.dec2006.com.

-gil

-----Original Message-----
From: [EMAIL PROTECTED]
[mailto:[EMAIL PROTECTED] On Behalf Of Charlie Kaiser
Sent: Thursday, February 09, 2006 7:42 AM
To: ActiveDir@mail.activedir.org
Subject: [ActiveDir] DR implementation planning

Hi all. 
We are finally getting our DR project going, and I'm looking for good
resources for design/implementation.

We have a small business; under 100 users. Running W2K3 AD (2 DCs in one
location), E2K3, Cisco Unity VM, home-grown intranet on IIS, LOB app
contained in-house. Around 30 remote SOHO users connecting via VPN.
Current backup consists of Backup Exec 9.x running backup-to-disk and
then copies to tapes which are moved and stored offsite.

I have relatively complete design authority, and am starting with a
clean slate. A couple of basic parameters. We will be building the DR
site in our parent company's datacenter and currently have frame
circuits to their corp net (not sure if we'll have direct to the data
center or not). We want to utilize HP blade servers and VMWare as much
as possible. The management goal is to virtualize the entire
infrastructure, although it is recognized that this may not be entirely
possible. We want the DR site to be fully vendor supported, so
virtualization will depend largely on vendor support. The site will be
required to support ~50% of our user base for up to 30 days. We would
prefer to avoid utilizing 3rd party replication apps and stick with
native tools if possible.

This will be a warm DR site with once-per-day replication with
production; recovery within 24 hours is the goal. Losing the current
day's work is acceptable. We have ~6 weeks for design and ~10 weeks
after that for build/test, including fire drill.

We start the design meetings today. I'm interested in pointers to any
good whitepapers, references, and recommendations. Also interested in
what has worked (or failed!) for others with similar criteria. While
there's no shortage of information on the net about DR planning and
implementation, I'm interested in what the experts here have found to be
valuable. I remember DEC a couple of years ago had some great DR stuff,
but my event logs have overwritten most of that by now, and I don't
remember if there was a proceedings DVD or anything on that. Plus, two
years is a long time; methods and the like have changed since then.

Thanks!

**********************
Charlie Kaiser
W2K3 MCSA/MCSE/Security, CCNA
Systems Engineer
Essex Credit / Brickwalk
510 595 5083
**********************
List info   : http://www.activedir.org/List.aspx
List FAQ    : http://www.activedir.org/ListFAQ.aspx
List archive:
http://www.mail-archive.com/activedir%40mail.activedir.org/
List info   : http://www.activedir.org/List.aspx
List FAQ    : http://www.activedir.org/ListFAQ.aspx
List archive: http://www.mail-archive.com/activedir%40mail.activedir.org/

Reply via email to