AW: AW: Replication Questions

2007-08-13 Thread Auer, Wolfgang
Hello Linos,


 If i not manually deactivate the units but i have a power failure and i
 have to reboot a server involved in the replication, do i have to
 manually activate the sync or it will be activated on reboot if i launch
 the messageserver and syncservice automatically, i can lost many data if
 i have to activate this manually after hardware/so failure.

It should be sufficient if you restart the messageserver and syncservices.

Regards
  Wolfgang 


Wolfgang Auer 
Developer 
MaxDBliveCache 
SAP AG 
mailto:[EMAIL PROTECTED] 
http://www.sap.com
 
Sitz der Gesellschaft/Registered Office: Walldorf, Germany 
Vorstand/SAP Executive Board: Henning Kagermann (Sprecher/CEO), Léo Apotheker 
(stellvertretender Sprecher/Deputy CEO), Werner Brandt, Claus Heinrich, Gerhard 
Oswald, Peter Zencke
 
Vorsitzender des Aufsichtsrats/Chairperson of the SAP Supervisory Board: Hasso 
Plattner 
Registergericht/Commercial Register Mannheim No HRB 350269 
 
Diese E-Mail kann Betriebs- oder Geschäftsgeheimnisse oder sonstige 
vertrauliche Informationen enthalten. Sollten Sie diese E-Mail irrtümlich 
erhalten haben, ist Ihnen eine Kenntnisnahme des Inhalts, eine Vervielfältigung 
oder Weitergabe der E-Mail ausdrücklich untersagt.
 
Bitte benachrichtigen Sie uns und vernichten Sie die empfangene E-Mail. Vielen 
Dank. 
 
This e-mail may contain trade secrets or privileged, undisclosed, or otherwise 
confidential information. If you have received this e-mail in error, you are 
hereby notified that any review, copying, or distribution of it is strictly 
prohibited. Please inform us immediately and destroy the original transmittal. 
Thank you for your cooperation.

--
MaxDB Discussion Mailing List
For list archives: http://lists.mysql.com/maxdb
To unsubscribe:http://lists.mysql.com/[EMAIL PROTECTED]



Re: AW: Replication Questions

2007-08-04 Thread Linos
Hello Wolfgang,

 2) If i deactivate the units and later activate them the changes made in
 this time are lost? (i refer to all the changes, client and master in a
 IN/OUT, if i only have out i know i can send content to client)
 
 = Yes. You have to do your changes while the application is not running. But 
 if you change the application tables, shouldn't the application be stopped 
 anyway?

If i not manually deactivate the units but i have a power failure and i
have to reboot a server involved in the replication, do i have to
manually activate the sync or it will be activated on reboot if i launch
the messageserver and syncservice automatically, i can lost many data if
i have to activate this manually after hardware/so failure.


 3) I would like to use sequence numbers in the structure (i have the
 possibility to use natural keys but any times with multiple columns, not
 too much practical), i have tried but when i create the sequence in the
 master it is not replicated in the client so i can not use the sequence
 in inserts into the client, can i use sequence numbers? what if about
 collision, the numbers that in my design can have a collision are
 meaningless because i haver other unique columns so i have no problem in
 automatically change them in the two databases if i have collision but i
 don't  know if i can do it an how.
 
 = Sequences are not replicated. Only the numeric values generated by them in 
 a table. So collision can occur for these values. 
You should combine the sequence values with some kind of database 
 identifier.
You have to define the sequence on every client.

Ok i will try to design this way.


Regards,
Miguel Angel.

-- 