*Press Release*

*September 21, 2008***

*ORISSA FLOOD DISASTER COULD HAVE BEEN AVOIDED: *

*WRONG OPERATION OF HIRAKUD DAM RESPONSIBLE*



The wrong operation of Hirakud Dam is majorly responsible for the current
flood disaster in Mahanadi basin in Orissa. Ever since Aug 1, 2008, when the
rule curve for current year came into operation, the Hirakud dam operators
have kept the water level at the Hirakud Dam way above the rule curve
recommended for the dam in 1988. Had the dam operated in a way to keep the
level below the recommended level, the current flood disaster could have
been avoided, it impact hugely reduced.



The water flow in Mahanadi river at Mundali barrage in the Mahanadi Delta
(at 1400 hours on 190908) was 14.6 lakh cusecs (cubic feet per second),
which increased (1200 hrs on 200908) to 15.81 lakh cusecs (see:
http://www.dowrorissa.gov.in/FLOOD/DailyFloodBulletin.htm), both way above
the safe limit of 10 lakh cusec, as recommended by the August 2007 report
(see: http://www.dowrorissa.gov.in/NEWS/Hirakud%20HLC/HirakudHLC.htm) of
"the High Level Committee to Study Various Aspects of Water Usage for
Hirakud Reservoir", appointed by the Government of Orissa. Out of the 14.6
lakh cusecs flowing in Mahanadi on 190908, over 4.62 lakh cusecs is released
by Hirakud dam. And by 1200 hours on 200908, the releases from the Hirakud
dam were increased to shockingly high 7.91 lakh cusecs. If Hirakud Dam had
not released the water when the downstream areas were experiencing heavy
rainfall, the amount the flow at Mundali barrage would have remained within
the safe limit of 10 lakh cusecs as recommended by the High Level Hirakud
Committee (HLHC), and there would have been no or hugely reduced flood
disaster.



The Hirakud dam operators were forced to release over 4.62 lakh cusecs on 19
Sept and 7.91 lakh cusecs on 20 Sept, because the water level at Hirakud dam
has already reached the Full Reservoir Level of 630 feet on Sept 18, 2008,
which should have been reached that level twelve days later on Sept 30, 2008.
And the water level at Hirakud has reached the full level so fast because
the operators had consistently kept the water level very high, way above the
recommended level.



For example, on Aug 1, 2008, the recommended water level at Hirakud dam was
590 feet (this is the dead storage level of Hirakud dam), but the actual
water level on that date was already way high at 607.5 feet. On Aug 13, 2008,
the water level was 618.5 feet, against the recommended level of 606 feet.
On Sept 10, 2008, the water level was 627 feet, just three feet below the
full level, when the recommended level was 623 feet.



Hirakud dam is one of the few dams of India where flood control cushion has
been provided in its storage capacity. The idea is that the flood cushion
portion of the storage should not be filled right till the end of the
monsoon, which is in the first week of Oct. By filling up the reservoir to
full capacity before the end of monsoon, the dam operators have destroyed
the flood control role of the Hirakud dam and thus brought an avoidable
flood disaster on the poor people of coastal Orissa districts. This disaster
could have been avoided or hugely reduced, had they operated the dam keeping
in mind the flood cushion role of the reservoir. In fact, similar incidents
had happened in 1982 and 2002 and it seems no lessons have been learnt from
those disasters, says well known flood expert Dinesh K Mishra of *Barh Mukti
Abhiyan*.



*Consequences* Look at the contours of the disastrous consequences of the
flood disaster: According to Engineer in Chief, Water Resources Department
of Orissa, this is the worst floods in Orissa since 1982. 20 lakh people of
2960 villages in 110 blocks and 870 gram panchayats in 17 districts
including Kendrapara, Jagatsinghpur, Puri & Cuttack have been affected, 1.8
lakh people are evacuated, hundreds are killed, embankments have breached at
28 places.



*Dubious Data of CWC *Here it may be added that the Central Water Commission
(CWC) of the Government of India has been using completely outdated figures
of reservoir capacities. For example, for Hirakud, while the HLHC has said
that the live storage capacity of Hirakud in 2007 was down to 4.647 Billion
Cubic Meters (BCM) (down from 5.818 BCM at the time of start up in 1957),
CWC's reservoir storage website (http://www.cwc.gov.in/Reservoir_level.htm)
says the Hirakud's live storage capacity is 5.378 BCM.  It is also shocking
to note that CWC's flood forecast site for the first time (during the
current phase) mentioned the Mahanadi floods only on September 19, 2008, *
after* the news was already out in the media. What is the value of such
forecasts of CWC?



*Will those responsible be held accountable? *The Orissa government needs to
answer to the people of Orissa and the nation, why this shocking manmade
disaster was allowed to happen and what it would do to ensure that those who
are responsible for the wrong operation of the Hirakud dam are held
accountable?



*Himanshu Thakkar ([EMAIL PROTECTED], Ph: 27484655; **Mobile**: 99682
42798)*

*South Asia Network on Dams, Rivers & People (www.sandrp.in) *




-- 
Sudhir Pattnaik

The Independent Media Group

Reply via email to