Assuming this is a zero instantaneous no export, not on the daily or
monthly. I have installed a few XW, and XW PRO inverters, however, I have
never done an instantaneous no export project on the entire service. The
problem is the load. Ideally you want to monitor the service entrance and
It can be done but it is not an easy job. You are 2 generations of XW
back.
XW+ was good at this and XW pro was designed for this
along with being able to charge based on Soc (from the BMS) as well as
voltage.
Is this an insured home? You might need a permit as this has to be
legal for
I’ve inherited a XW. 6048 system that we just installed a LiFePO4 battery bank
with.
Has anyone successfully used Grid Support with Sell disabled?
This system never had an Interconnection Agreement with the utility co so it
cannot sell.
Currently we have :
AC charger on , Multi Stage
PV