Sounds great Jaime!
Josh Reynolds
CIO, SPITwSPOTS
[email protected]
www.spitwspots.com
On 2/9/2015 12:30 PM, Jaime Fink wrote:
All that matters is under what set of Part 15 rules a manufacturer
certified under.
You can’t get the higher power U-NII 1 without certifying under the
new NPRM issued last May 2014 which have the more restrictive U-NII 3
OOBE limits, otherwise you’re restricted to prior lower U-NII 1 PTMP
power levels.
In the new NPRM which opened up the higher power 53 dBm EIRP limits
for U-NII 1, there are specific OOBE limits to that band to protect
both sides of the U-NII 1 band including Globalstar (5.096-5.25 GHz) ,
so it’s pretty impossible to get certified at 53 dBm EIRP and there’s
a 30-degree elevation limit on PTP operation to protect their
satellite transmissions in the sky as they overlap with U-NII 1 band.
As of beginning of June, everyone will have to certify under that new
rule and pass the new DFS requirements to operate in U-NII 2.
By example, Mimosa passed the new regulations on our Backhaul products
including the latest stringent DFS tests, therefore got access to
higher power in U-NII 1, but were forced to back off power in our
certification a bit in U-NII 1 and U-NII 3 (different levels for each
band) from max theoretical due to OOBE impacts.
The U-NII 1 is a topic we’re working to address with the FCC via
WISPA/Cambium/Jab/Mimosa et al in unison with the U-NII 3 OOBE changes
we’re working together to fix. Very close to done with a new unified
proposal that we can finally take back to the FCC.
Cheers,
*Jaime Fink* • *Mimosa* <http://www.mimosa.co> • *CPO & Co-Founder*
300 Orchard City Dr Ste 100 • Campbell • CA 95008
This email may contain confidential and privileged material for the
sole use of the intended recipient(s). Any review, use, distribution
or disclosure by others is strictly prohibited. If you are not the
intended recipient (or authorized to receive for the recipient),
please contact the sender by reply email and delete all copies of this
message.
On Feb 9, 2015, at 12:59 PM, Mathew Howard <[email protected]
<mailto:[email protected]>> wrote:
The theoretical max is 53dBm EIRP, but nothing is actually certified
for that high of power because of OOBE, so how high of power you can
actually use is very dependent on the specific radio you're using.
It is available on PTP650... I think it requires a free key to unlock.
On Mon, Feb 9, 2015 at 2:49 PM, Mike Hammett <[email protected]
<mailto:[email protected]>> wrote:
Closer to 5.8 than 5.1, but there were a bunch of other changes
relating to OOBE.
-----
Mike Hammett
Intelligent Computing Solutions
http://www.ics-il.com <http://www.ics-il.com/>
------------------------------------------------------------------------
*From: *"Rory McCann" <[email protected]
<mailto:[email protected]>>
*To: *[email protected] <mailto:[email protected]>
*Sent: *Monday, February 9, 2015 2:48:57 PM
*Subject: *[AFMUG] 5.1 Band FCC
I must've been under a rock when this was discussed because I knew
absolutely nothing about it.
So 5.1GHz is legal for outdoor use in the US? If so, what are the
power
requirements (ie: is it more aligned with 5.4GHz or 5.7GHz?)
Also, is it
available for use on deployed PTP650 products?
Thanks!
--
Rory McCann
MKAP Technology Solutions
Web: www.mkap.net <http://www.mkap.net/>