I am with Kurt. Mods are usually easier to get permits for. Leave the
concrete base dig around it a bit and cover it up with more concrete. I had
a SS tower fall and I used the same base and sifted the tower feet 90
degrees. It was all a modification or upgrade.

On Thu, Feb 9, 2017 at 10:15 AM Jaime Solorza <[email protected]>
wrote:

> Can you use the existing one to help you erect new one?   I have done
> that.... Really helps as long older tower is sound.
>
> On Feb 9, 2017 9:04 AM, "Gino Villarini" <[email protected]> wrote:
>
> So we inherited this 80; Rohn 55 type guyed tower that needs to be
> replaced… Its currently installed on a State Forest area, so building a new
> one besides it (new foundation) seems next to imposible (permit wise).
>
> I was thinking of ways to build one over the existing one…
>
> Any ideas?
>
>
>
> *Gino Villarini*
> President
> Metro Office Park #18 Suite 304 Guaynabo, Puerto Rico 00968
>
>