On 4 Aug, 2009, at 20:18 , rstacy wrote:
Hi Stacy, > I have recently established a release backlog. I have set the scope > of the backlog to milestone, and enabled strict setting. However, > when I click the view release backlog button, I see tickets that are > not scheduled for the release. Many of the tickets in the backlog are > scheduled for past releases or have a value of N.A. Am I missing > something? Probably not... in that backlog will appear all the Requirements that have been planned for that milestone, and with them all the User Stories connected to the requirement, that are not explicitly planned for Sprints outside of that milestone, this is the idea at least. So which kind of ticket that shouldn't be there do you see? We need a bit more of information to help you ;-) Best ANdreaT --~--~---------~--~----~------------~-------~--~----~ You received this message because you are subscribed to the Google Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH http://www.agile42.com and is focused in supporting Agilo for Scrum users. To post to this group, send email to [email protected] To unsubscribe from this group, send email to [email protected] For more options, visit this group at http://groups.google.com/group/agilo?hl=en -~----------~----~----~----~------~----~------~--~---

