Hi Shikarishambu, > I have created a milestone and a sprint under it. I have a number of > user stories, tasks and bugs that are part of the sprint. We have > assigned story points to the items and committed the sprint backlog. > > The burndown chart does not seem to reflect the values we have. In > fact, it shows the default value - from 400 to 0. It does not seem to > show actual burndown or trend. Similarly, the sprint commitment graph > is blank. Only the sprint tickets graph seems to work.
First off, did that sprint actually start yet? The Burndown chart is time based, so you only see something in the interval of the sprint actually happening. Regards, Martin -- Follow Agilo on Twitter: http://twitter.com/agiloforscrum ----- You received this message because you are subscribed to the Google Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH http://www.agile42.com and is focused in supporting Agilo for Scrum users. To post to this group, send email to [email protected] To unsubscribe from this group, send email to [email protected] For more options, visit this group at http://groups.google.com/group/agilo?hl=en