Update (should have been waiting a few more minutes with my last post
- sorry for that):
I was now able to reproduce it on the XP machine. Think I'm close to
the source of the problem now.

New Installation.
- login as po
- create a new sprint s1
- create a new userstory u1 (assign it to sprint s1, USP=5, assign to
user po)
- create a new userstory u2 (assign it to sprint s1, USP=5, assign to
user po)
- logout
- login as mary
- break up the sprints into two tasks each (task1a, task1b for u1;
task2a, taks2b for u2). Assign each task to user mary. Set remaining
time to [task1a: 2h,  task1b: 1h, task2a: 3h, task2b: 2h]
- logout
- login as sm
- view sprint backlog for s1
- mark the userstory u1 and the linked tasks task1a and task1b and hit
"remove selected"
- logout
- login as po
- go to the product backlock, view the details for the userstory u1,
edit details, and assign it to sprint s1 (again)
- logout
- login as sm
- view the sprint backlog for s1
- mark both userstories and hit "calculate story points/time"

I got total time of 12h now, instead of 2+1+3+2 = 8h.

Regards, Ckoenig

-- 
Follow Agilo on Twitter: http://twitter.com/agiloforscrum
-----
You received this message because you are subscribed to the Google
Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH 
http://www.agile42.com and is focused in supporting Agilo for Scrum users.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo?hl=en

Reply via email to