Hi,
There is something wrong with burndown during weekends. It seems that
it correctly marks weekends with gray, but then the burndown lines
(both actual and ideal) goes down through saturday.

http://users.vlo.gda.pl/~okrasz/files/burndown2.jpg

Then on monday goes down with just one day flat but then on tuesday it
will make the monday flat and set the burndown from monday to
tuesday.

http://users.vlo.gda.pl/~okrasz/files/burndown.jpg

It happens on 0.8.4.1 but it was also happening on 0.8.3. I'm in
Central European Timezone (GMT +1). In 0.8.3 I was applying one of the
timezone burndown patches but it wasn't for this problem.

Any ideas what is wrong?

-- 
Follow Agilo on Twitter: http://twitter.com/agiloforscrum
-----
You received this message because you are subscribed to the Google
Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH 
http://www.agile42.com and is focused in supporting Agilo for Scrum users.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo?hl=en

Reply via email to