Hello, My team started to use Agilo tool for organizing our work and make it more effective. But we faced such interesting situation: during the 2 weeks Sprint we have to add some 'ad hoc' User Stories into Sprint Backlog that require immediate resolution Yes, I know that Sprint Backlog should be unchanged during the Sprint but it is specific of our activities. Sad.
So, what we do in general: create new User Story, set Story Points, Assign it to Story Owner and split it into the set of Tasks with Task Owners. Then such User Story is accepted and we start to implement it. Everything is fine but! Actual\Ideal Burndown Chart shows no increased Sprint Backlog, it looks like we have no new User Story and fixing it gives us decreasing of Actual Burndown but it is false decreasing since we previously increased our volume of tasks by new hours in new User Story. It looks that if we pressed Confirm Commitments then all other including User Stories will no affect Burndown graphic. Is it correct? Could you advice how we can organize\manage our Sprint in Agilo tool in order to show on Charts our real changing of Sprint Backlog? In order to see that incoming User Stories during Sprint increased in Chart Ideal Burndown line (make it higher in graphic) and we can see that we should apply more forces to match with Actual Burndown line. -- Follow Agilo on Twitter: http://twitter.com/agiloforscrum ----- You received this message because you are subscribed to the Google Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH http://www.agile42.com and is focused in supporting Agilo for Scrum users. To post to this group, send email to [email protected] To unsubscribe from this group, send email to [email protected] For more options, visit this group at http://groups.google.com/group/agilo?hl=en