Hello, Robert, > Are you sure your added story is not counted for the ideal/actual > burndown? What should happen when you add or remove a story mid-sprint > is that its tasks are added to the actual and ideal burndown of all > previous days, as if the story had been there right at the sprint start > (or, for removal, as if the story had never been part of the sprint). > Can you confirm this behavior with your installation?
Yes, I see now that it works as you described it above. The reason why I saw no this is just "its tasks are added to the actual and ideal burndown of all previous days", so it gave us small increase per day. Thank you! -- -- Follow Agilo on Twitter: http://twitter.com/agiloforscrum Please support us by reviewing and voting on: http://userstories.com/products/8-agilo-for-scrum http://ohloh.net/p/agilo-scrum http://freshmeat.net/projects/agiloforscrum You received this message because you are subscribed to the Google Groups "Agilo for Scrum" group. This group is moderated by agile42 GmbH http://www.agile42.com and is focused in supporting Agilo for Scrum users. To post to this group, send email to [email protected] To unsubscribe from this group, send email to [email protected] For more options, visit this group at http://groups.google.com/group/agilo?hl=en