Hello, We're using a calculated property for the remaining_time field on stories, but we have a problem. Some stories are "re-used" in several sprints, but the task are new in each sprint.
So for example, in Sprint 1, I have Story 1, with task 1 and 2. Those tasks are unfinished, so their remaining time is 5hours each. Then we create a new sprint, assign story 1 to that sprint, and create tasks 3 and 4 to that story. Those have remaining time 3 hours. The problem is that the backlog view calculate the total remaining time using every task linked to the story, not just the tasks in the current sprint. So I have a total remaining time for story 1 of 16 hours, when I should get 6. So my question is, is there any way to filter in the calculated property by current sprint? Or even by taks status? Thanks! -- Follow Agilo on Twitter: http://twitter.com/agiloforscrum Please support us by reviewing and voting on: http://userstories.com/products/8-agilo-for-scrum http://ohloh.net/p/agilo-scrum http://freshmeat.net/projects/agiloforscrum You have received this message because you are subscribed to the "Agilo for Scrum" Google Group. This group is focused on supporting Agilo for Scrum users and is moderated by agile42 GmbH <http://www.agile42.com>. To post to this group, send email to [email protected] To unsubscribe from this group, send an email to [email protected] For more options, visit this group at http://groups.google.com/group/agilo