Hello Adolfo,

On Monday 26 July 2010, Adolfo Gonzalez wrote:
> We're using a calculated property for the remaining_time field on
> stories, but we have a problem. Some stories are "re-used" in several
> sprints, but the task are new in each sprint.
> [snip]

Are you sure you're doing Scrum? You should not have one story be part 
of two concurrent sprints. If two teams work on two different sets of 
tasks, you have two stories right there. Otherwise, how do you measure 
estimations, commitment and completion? If the sprints are serial, the 
tasks in the previous sprint have a remaining time of 0 -- so they do 
not matter in the total remaining time calculation.


Cheers
Robert

-- 
Follow Agilo on Twitter: http://twitter.com/agiloforscrum
Please support us by reviewing and voting on: 
http://userstories.com/products/8-agilo-for-scrum 
http://ohloh.net/p/agilo-scrum 
http://freshmeat.net/projects/agiloforscrum

You have received this message because you are subscribed to
the "Agilo for Scrum" Google Group. This group is focused on
supporting Agilo for Scrum users and is moderated by
agile42 GmbH <http://www.agile42.com>.

To post to this group, send email to [email protected]
To unsubscribe from this group, send an email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo

Reply via email to