Hi ruph,
Am 06.08.2010 13:26, schrieb ruph:
I have a question regarding the Contingents. We've reserved some time
for unplanned support activities as you've suggested in your release
notes. Now one critical bug emerged the team must urgently fix. What
would be the usual way of removing time from Contingents?
Basically you go to the sprint backlog, open the contingents and enter
the time you used in the input field. Afterwards the contingent shows
that there was some time used up.
The burndown chart will not be affected by that as the contingent time
was deducted from the capacity from the beginning.
hope that helps,
fs
--
Follow Agilo on Twitter: http://twitter.com/agiloforscrum
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-scrum
http://freshmeat.net/projects/agiloforscrum
You have received this message because you are subscribed to
the "Agilo for Scrum" Google Group. This group is focused on
supporting Agilo for Scrum users and is moderated by
agile42 GmbH <http://www.agile42.com>.
To post to this group, send email to [email protected]
To unsubscribe from this group, send an email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo