Hi,
Am 03.08.2010 18:27, schrieb culliard:
Anyway I have an issue getting 'velocity' (actual number of story
points completed) to display on Team metrics. We have completed 2
iterations
The number will be stored only when you 'close' a sprint (roadmap, click
on sprint name).
Would I be able to fix this for the 2 iterations we have done? Details
of our components are below.
I think this should be possible if you 'close' these sprints as
described above.
fs
--
Follow Agilo on Twitter: http://twitter.com/agiloforscrum
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-scrum
http://freshmeat.net/projects/agiloforscrum
You have received this message because you are subscribed to
the "Agilo for Scrum" Google Group. This group is focused on
supporting Agilo for Scrum users and is moderated by
agile42 GmbH <http://www.agile42.com>.
To post to this group, send email to [email protected]
To unsubscribe from this group, send an email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/agilo