On Feb 17, 2015, at 11:54 AM, David Huberman 
<[email protected]<mailto:[email protected]>> wrote:

But “something quite so fuzzy” is your interpretation, not ARIN’s.   So let’s 
get ARIN’s interpretation and try and take the fuzziness out of the equation.

Question for ARIN:  In the general (normal) case when an application is made 
for EU v6 under clause e) and there’s a technical explanation for why they want 
RIR-issued space, will the application be approved ?

Yes, so long as a technical explanation is provided.   NRPM 6.5.8.1 provides a
list of several situations that would warrant direct end-user IPv6 assignment,
and others are accepted as well so long as a reasonable technical justification
is provided.

Thanks,
/John

John Curran
President and CEO
ARIN

_______________________________________________
PPML
You are receiving this message because you are subscribed to
the ARIN Public Policy Mailing List ([email protected]).
Unsubscribe or manage your mailing list subscription at:
http://lists.arin.net/mailman/listinfo/arin-ppml
Please contact [email protected] if you experience any issues.

Reply via email to