Hi Samuel

Try putting the excluded days in the holidays list in US format - 2/28/2007
and see if that works

HTH

David Sanders
Remedy Solution Architect
Enterprise Service Suite @ Work
==========================
ARS List Award Winner 2005
Best 3rd party Remedy Application
 
tel +44 1494 468980
mobile +44 7710 377761
email [EMAIL PROTECTED]
 
web http://www.westoverconsulting.co.uk
 

-----Original Message-----
From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of Shibu Samuel
Sent: Thursday, March 22, 2007 12:39 PM
To: [email protected]
Subject: Help

Hi All, 
 
I have a menu with data in the following format:
 
FEB-07
APR-08
MAY-09
 
When one of this is selected, the data needs to be converted into the last
working day of the particular month for the particular year on submit.
I'm using the Application-Bus-Time-Add Process to calculate the last working
day but the problem is that though I've entered 28/02/2007 in the holiday
list of the the Business Time Holidays form, when I use the following
command in the Set Fields $PROCESS$ @@:Application-Bus-Time-Add
"$fieldname$" "19" "4" "Holidays" "Workdays" I get the result as 28/02/2007
which is incorrect. 

There is a temp field that sets the date to 01/02/2007 when FEB-07 is
selected.

What am I doing wrong that the holiday is not considered and is displayed as
the last working day.
 
Thanks in advance.
 
 
Thanks 
Shibu Samuel 
 

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org ARSlist:"Where the 
Answers Are"

Reply via email to