I want to know if its possible to report on time spent in Pending
status.
Lets say i take a ticket from Assigned to pending to resolved. I know
you can report on the status.history field to find the different times
in each state.

My question is if i then take the ticket from resolved back to pending,
the status.history pending field in the reporting tool is overwritten
with the new time.
 
I want to know if it is possible to report on how much total time is
spent in each status.
 
Thanks    
 

Rob Cvetkovski, Associate Consultant

Burntsand Inc.  
185 The West Mall Suite 600 Toronto ON M9C 5L5
Tel: (416) 234-3839  Cell: (416) 917-7231
www.burntsand.com <http://www.burntsand.com/> 

 

 