This is what Remedy tells me.  So since the defect is "Work in
Progress" I will have to create my own workflow / escalation to "auto
close" the Change tickets.



On 2/20/08, Lammey, Peter A. <[EMAIL PROTECTED]> wrote:
> I never heard about this.
> I just did a lookup and I can see that indeed Change tickets that were
> marked Completed over a month ago are still in a Status of Completed.
>
> They should be moved to "Closed" with Status Reason of "Successful"
> right? (if they were left there in Completed status for at least 15
> days)
>
>
>
> Thanks
> Peter Lammey
> ESPN MIT Technical Services & Applications Management
> 860-766-4761
>
> -----Original Message-----
> From: Action Request System discussion list(ARSList)
> [mailto:[EMAIL PROTECTED] On Behalf Of T. Dee
> Sent: Wednesday, February 20, 2008 11:20 AM
> To: [email protected]
> Subject: Defect: Auto-Close - Change - ITSM 7
>
> Just an FYI - the auto close in Change does not work.
>
> This is observed as a bug and already a defect SW00275623 is logged for
> the same. The defect status is in work in Progress.
>
> ________________________________________________________________________
> _______
> UNSUBSCRIBE or access ARSlist Archives at www.arslist.org Platinum
> Sponsor: www.rmsportal.com ARSlist: "Where the Answers Are"
>
> _______________________________________________________________________________
> UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
> Platinum Sponsor: www.rmsportal.com ARSlist: "Where the Answers Are"
>

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: "Where the Answers Are"

Reply via email to