Great :) It works now . thanks so much,

BnB,

On May 28, 4:48 pm, "T. Dee" <[EMAIL PROTECTED]> wrote:
> You can not start working on the Task(s) until the Change is in
> "Implementation in Progress".
>
> On 5/28/08, Bulls-n-Bears <[EMAIL PROTECTED]> wrote:
>
>
>
> > Greetings All,
>
> > Am trying to create a new change ticket using a change template. The
> > ticket got created successfully . When I now switch to Tasks tab and
> > try closing a task with Status reason as "Success"., I recieve the
> > following error.
>
> > "This task (or group)  must be activated (from the parent) before it
> > can be changed to the status:  Closed Success (ARERR 45093)".
>
> > The change ticket is freshly created. The Task template is
> > successfully attached to the ticket and I'm seeing the three tasks
> > coming in from the template in Tasks tab.
>
> > My env : ITSM 7.0 on Solaris and User Tool ( 7.0) on WinXP.
>
> > Any ideas how to fix this ?
>
> > Cheers,
> > BnB
>
> > _______________________________________________________________________________
> > UNSUBSCRIBE or access ARSlist Archives atwww.arslist.org
> > Platinum Sponsor:www.rmsportal.comARSlist: "Where the Answers Are"
>
> _______________________________________________________________________________
> UNSUBSCRIBE or access ARSlist Archives atwww.arslist.org
> Platinum Sponsor:www.rmsportal.comARSlist: "Where the Answers Are"

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor: www.rmsportal.com ARSlist: "Where the Answers Are"

Reply via email to