Rick,
I don't know if it is a known issue but I have seen it working correctly
under CM 7.0.3 p8.  We don't use that part of the approval flow here but if
I use it it works.

Regards,
Chuck Baldi

On Mon, Jan 11, 2010 at 1:58 PM, Rick Cook <[email protected]> wrote:

> ** I have CM 7.0.3 P9, and am seeing something that doesn't make sense.  So
> either it isn't working as designed, or I don't understand the design.
>
> After the Business Approval is processed, the Status is Scheduled.  In
> either case, the PF Bar should allow the Change User at that point to select
> "Next Stage" from the PF Bar to move that into a Status of "Implementation
> in Progress".  This is not working.  I can change the Status manually, but
> not from the PF Bar.
>
> The same is true when attempting to use the PF Bar from "Planning in
> Progress" to "Scheduled for Review".  Manually, it works just fine.  With
> the PF Bar, not so much.
>
> Both processes use the same part of the PF Bar.  Is this a known issue with
> a resolution, or just something we are going to have to work around, or is
> this "As designed".
>
> Rick
> _Platinum Sponsor: [email protected] ARSlist: "Where the Answers
> Are"_

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor:[email protected] ARSlist: "Where the Answers Are"

Reply via email to