OK, thanks.  Must be something I did then.

Rick

On Mon, Jan 11, 2010 at 1:38 PM, Charles Baldi <[email protected]>wrote:

> **
> Rick,
> I don't know if it is a known issue but I have seen it working correctly
> under CM 7.0.3 p8.  We don't use that part of the approval flow here but if
> I use it it works.
>
> Regards,
> Chuck Baldi
>
> On Mon, Jan 11, 2010 at 1:58 PM, Rick Cook <[email protected]> wrote:
>
>> ** I have CM 7.0.3 P9, and am seeing something that doesn't make sense.
>> So either it isn't working as designed, or I don't understand the design.
>>
>>
>> After the Business Approval is processed, the Status is Scheduled.  In
>> either case, the PF Bar should allow the Change User at that point to select
>> "Next Stage" from the PF Bar to move that into a Status of "Implementation
>> in Progress".  This is not working.  I can change the Status manually, but
>> not from the PF Bar.
>>
>> The same is true when attempting to use the PF Bar from "Planning in
>> Progress" to "Scheduled for Review".  Manually, it works just fine.  With
>> the PF Bar, not so much.
>>
>> Both processes use the same part of the PF Bar.  Is this a known issue
>> with a resolution, or just something we are going to have to work around, or
>> is this "As designed".
>>
>> Rick
>> _Platinum Sponsor: [email protected] ARSlist: "Where the Answers
>> Are"_
>
>
> _Platinum Sponsor: [email protected] ARSlist: "Where the Answers
> Are"_

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org
Platinum Sponsor:[email protected] ARSlist: "Where the Answers Are"

Reply via email to