Hello dha,
We have checked the issue. If your task is of 8 hour and your work lines
is also of 8 hours the progress bar set to 99%, it is quite obvious because
task is still not completed so as soon as you will say task is done the
progress bar will reach to 100% and we can say that the task is done.
Thank You
** Changed in: openobject-addons
Status: Confirmed => Invalid
--
You received this bug notification because you are a member of C2C
OERPScenario, which is subscribed to the OpenERP Project Group.
https://bugs.launchpad.net/bugs/751401
Title:
[PS] Problem with progression bar while encoding work done
Status in OpenERP Modules (addons):
Invalid
Bug description:
trunk, revno 3377
* Project/Project/Task, encode a new task with planned amount 8 hours
* Start the task and indicate you work on it for 8 hours
Obtained result : The progression bar is now at 99.9%
Expected result : the progression bar indicates 100%
reported by dha, OpenERP Prof. Services
_______________________________________________
Mailing list: https://launchpad.net/~c2c-oerpscenario
Post to : [email protected]
Unsubscribe : https://launchpad.net/~c2c-oerpscenario
More help : https://help.launchpad.net/ListHelp