Title:
  [trunk][purchase]Scheduled date in past when lead time is one day

Status in OpenERP Addons (modules):
  Fix Released

Bug description:
  My scenario:
  Supplier has a one day lead time for all material order prior to 2PM the 
previous day. So I set Purchase delay to 0 on the company form and supplier 
delay to 1 on the product form. The product is MTS with a automatic orderpoint 
configured. 

  Result:
  The orderpoint generated purchase order is one day in the past. 

  It also appears that you cannot use a delay of 0, though this wouldn't really 
make sense in this scenario. 
  I'm not sure the way the requested date works makes sense either - it appears 
that the formula for requested date is PO sched'd date - seller delay. Why 
would the request date include the seller delay, shouldn't that only be used 
for internal calculation? If a seller has a delay of 10 days and I want 
something 10 days in the future, it puts a req'd date of today?

To manage notifications about this bug go to:
https://bugs.launchpad.net/openobject-addons/+bug/808602/+subscriptions

_______________________________________________
Mailing list: https://launchpad.net/~c2c-oerpscenario
Post to     : [email protected]
Unsubscribe : https://launchpad.net/~c2c-oerpscenario
More help   : https://help.launchpad.net/ListHelp

Reply via email to