Kudos Rocky n maf!!!

What or how much are the other executive members contributing to this
initiative? It is very important that the executives spearheaded such
efforts, 300g is doable guys,  dip in your pockets n give back

May be basmal can assist too! May be may bee.

Sule

On Jun 21, 2010 7:01 PM, "Mafuleka Barlett (Mr)" <[email protected]>
wrote:

 CEZOBAL FAMILY,

 Please be advised that the CEZOBAL Executive Committee will be carrying out
some rehabilitation work on Silver Stadium during the Mid-Season break to
try and improve the standard of the Silver basketball court. CEZOBAL is a
big family and if we were to come together and help each other in this
initiative it will benefit all of us and the generations to come. I have
listed below materials which will be needed to help with the rehabilitation
of the court. Those of you who feel they can assist with some materials
listed below please contact me on 099 9919 328 and we will make arrangements
on when the materials you would like to assist with will be needed.



The following are the works which we plan to carry out using the listed
materials below:-

1.      Reworking and plastering the existing 3 stands.

2.      Building an additional 2 stands on top of the existing 3 stands and
plaster them as well. The extra 2 stands are to act as protective cover for
all the water and sand which move from higher ground onto the existing
stands as well as the playing surface.

3.      Drainage for the water which comes from the high ground

4.      The boards will be reworked and block board will be put on the front
of the hoops so as to avoid the ball bouncing off the board in an awkward
way. The block boards will be painted 3 coats of oil paint so as to protect
them to last a long time.

5.      Resurfacing the cracked areas around the playing area, and painting
most of the playing area with different colours.





*ITEM*

*UNIT*

*QUANTITY*

*ESTIMATED UNIT RATE*

*TOTATL COST*

Cement

Bags

50

MK2,700

MK135,000

Sand

Trips

5

MK12,000

MK60,000

Quarry Stone

Trips

3

MK15,000

MK45,000

Bricks

Trips

1

MK30,000

MK30,000

Paint

5 Litre tins

6

MK6,000

MK36,000

Block board

board

2

MK6,000

MK12,000

*Total estimated cost of Materials*

*MK318,000*





You will notice that the cost of the installation of the floodlights has not
been included on the above list this is because we are yet to find out how
much it will cost. The poles which were donated by Alliance One have been
worked on and have been painted all what is left is them to be planted on
the Silver Court, but before this is done, the work listed above has to be
carried out. Rocky Kaunda has offered to have his boys to do all the work
once the materials are available and he will pay for their labour charges.





 POWERED BY THE FOLLOWING SPONSORS:-







*                **“In Your Face”*



-- 
http://soyapi.com/owinna/cezobal2008
===================================
You received this message because you are subscribed to the Google
Groups "Central Zone Basketball League" group.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/cezobal?hl=en

-- 
http://soyapi.com/owinna/cezobal2008
===================================
You received this message because you are subscribed to the Google
Groups "Central Zone Basketball League" group.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
For more options, visit this group at
http://groups.google.com/group/cezobal?hl=en

<<image009.jpg>>

<<image007.jpg>>

<<image006.jpg>>

<<image001.jpg>>

<<image008.jpg>>

Reply via email to