We have a question about project dependency -
We are successfully able to create the BIRT integration build. But BIRT has
some other project dependencies, so far seems GEF and WTP still haven't
released the RC1 build yet, should BRIT build wait until the depending project
RC1 build ready or just use their latest integration build? GEF has the latest
integration build as 3.9.100 (2014/05/17)<javascript:toggle('rI201405170205')>
and wtp seems only have the
3.6.0M7<http://download.eclipse.org/webtools/downloads/drops/R3.6.0/S-3.6.0M7-20140505163128/>
build.
thanks
--Rima