Right now, Jira lists the following scheduled release dates: * 1.5.1 : 2013-07-24 * 1.4.5 : 2013-10-31 * 1.6.0 : 2013-11-24
I'd like to update these to reflect when we currently think things are likely to complete. Here's my WAG: * 1.5.1 : 2014-02-28 * 1.4.5 : 2014-03-19 * 1.6.0 : 2014-05-29 My reasoning: * 1.5.1 RC2 failed due to a miscommunication, RC3 is unlikely to have issues * AFAIK, 1.4.5 still needs to go through most of the long run tests and that will take time. I'd like to wait to start until we have lessons from the 1.5.1 release in hand. * 1.6.0 still has a ton of tickets, that date is based on a net burn down rate of just over 1 per business day (after adjusting for the time it takes to do tests) Thoughts? -Sean